Progress to date
- Four18 Architects appointed
- Community engagement undertaken
- Project updates via bulletins and the BCH website
- Building design completed
- Planning approval granted for the redevelopment
- Competitive tender conducted for a builder
- Loaram Constructions appointed
- Demolition completed
- Concrete slab completed
- Framing completed
COVID-19 impact
The COVID-19 pandemic has dramatically impacted construction costs.
It has been challenging to work within our funding budget.
To meet budget requirements, we have reviewed some features from the original plans.
This includes a reduction in the building’s size.
Next steps target dates
- Loaram Constructions on site January 2022
- Construction completed within 12 months of start date.
Please note: target dates may change because of COVID-19 lockdown restrictions.